The General Electricity Company announced the start of massive overhaul works at the third gas turbine of Al-Ruwais power plant in Nufusa Mountain.

The overhaul work will take four to five weeks, and will be carried out by the company's technicians and engineers, in cooperation with specialists from the German company Siemens, according to GECOL statement on its Facebook account, Friday.

The statement explained that these works come within the company's plans to increase production capacity, as the capacity of the third turbine at the Ruwais station is 145 megawatts.