The General Electricity Company confirmed, on Saturday, the completion of charging of the Fajij-Ubari 220 kV circuits, to contribute to the transfer of energy produced from Ubari
The General Electricity Company of Libya (GECOL) has concluded a settlement agreement with the owners of the properties located in the path of the electric transmission
The state's electricity company (GECOL) has carried out operational tests for the first unit of the Ubari Gas Power Plant southwest of Libya, confirming it had succeede
The General Electricity Company of Libya (GECOL) said it had connected Ubari substation with the electrical grid as part of its plans to take advantage of the full energy produce
The General Electricity Company of Libya (GECOL) said it had re-operated the second unit of Ubari gas power plant after finishing all tests, saying the unit that genera
The General Electricity Company of Libya (GECOL) discussed on Wednesday the completion of the Ubari gas power station project, in order to operate the first and second turbines,
The General Electricity Company of Libya confirmed the reconnecting of the third and fourth units of Ubari Gas Station to the electrical grid, with a production capacity of 252 M
The General Electricity Company of Libya has warned that the newly operated fourth turbine of Ubari power plant will be shut down once the oil stock operating it runs out.